Rights of Man Pub Roof Terrace, Lewes

Levelling an Uneven Roof Without Penetrating the Waterproofing: Rights of Man, Lewes

Completed roof terrace at the Rights of Man in Lewes

Project: Rights of Man public house, Lewes, East Sussex

Architect: Mackellar Schwerdt Architects

Main contractor: JH Payne Building Contractors

System: BalcoDeck® integrated non-penetrative decking and balustrade system

Balustrade: Milano, black finish

Terrace area: Approximately 83 m²

Balustrade length: Approximately 25 linear metres

Installation duration: 11 working days

Installation period: Spring 2026

The challenge: a leaking, uneven roof above a historic Lewes pub

Replacing the roof terrace at the Rights of Man in Lewes presented a combination of challenges familiar to architects working with older buildings.

The existing roof had experienced water ingress, including problems associated with rooflights. Its construction was not at a consistent level: the roof over the kitchen stood higher than the adjoining roof area above the pub.

The client wanted a new, usable terrace extending across these differing levels, with a contemporary deck and balustrade appropriate to the building's setting.

But the project team also wanted to avoid introducing new penetrations through the renewed waterproofing.

The challenge was therefore threefold: resolve the existing roof condition, create a level finished terrace above an irregular structure, and provide a structurally adequate guarding system without relying on conventional fixings through the roof membrane.

The building's location in the historic centre of Lewes added a further complication. Narrow streets and restricted access meant that the delivery and lifting strategy had to be carefully coordinated.

The roof before refurbishment Select an image to enlarge

The step between the two levels of the original timber decking
The exposed roof after the original decking was stripped out

A different approach to the roof terrace

Mackellar Schwerdt Architects identified BalcoDeck® while investigating potential solutions for the project and contacted Balconette in January 2025.

The original project drawings had included a different terrace system.

Following the enquiry, Balconette's team visited the site and discussed the project requirements with the architects.

The discussions focused on how the decking, guarding and waterproofing could be coordinated as a complete arrangement.

The existing rooflights were removed, and the roof was subsequently sealed as part of the refurbishment works.

The intention was to establish a renewed waterproofing layer beneath the terrace and avoid introducing new guarding fixings through it.

BalcoDeck® was selected as an integrated non-penetrative decking and balustrade solution.

Rather than treating the deck supports and balustrade anchorage as unrelated construction packages, the system allowed the project team to consider the supporting frame, finished deck and guarding together.

The architects proposed the system to their client. Following approval and appointment of the main contractor, JH Payne Building Contractors placed the order.

Creating one level across different roof heights

One of the project's defining technical challenges was the variation in the existing roof levels.

The roof over the kitchen was higher than the adjoining roof area above the pub.

The client wanted a consistent finished terrace level across the approximately 83 m² area.

This required the supporting structure to accommodate different distances between the existing roof surfaces and the proposed walking level.

The adjustable, telescopic characteristics of the BalcoDeck® support arrangement allowed the design to respond to those variations.

The supporting frame could be configured to establish a consistent finished deck level above the uneven roof construction.

This was more than a visual improvement.

A coordinated finished level affected the geometry of the terrace, the positioning of the balustrade and the relationship between the decking and the surrounding building.

It also allowed the underlying roof construction and waterproofing to remain distinct from the finished walking surface.

The design also considered how loads would be transferred into the existing roof structure and waterproofing build-up.

Levelling the terrace Select an image to enlarge

Roof surface and adjoining construction at the start of installation
Frame members and levelling equipment on the roof
Wide view of the supporting frame before decking was laid

Protecting the renewed waterproofing

The previous water-ingress problems made the waterproofing interface particularly important.

Once the existing rooflights had been removed and the roof sealed, the project team wanted to avoid introducing new penetrations for the terrace balustrade.

Conventional guarding arrangements often rely on structural connections through the roof build-up or into adjoining structural elements.

Such connections can be successfully designed and waterproofed, but they require coordinated detailing and introduce additional interfaces.

At the Rights of Man, the selected BalcoDeck® arrangement provided an alternative.

The integrated supporting system allowed the decking and guarding to be designed without the conventional balustrade fixing penetrations through the renewed roof membrane.

This addressed one of the project's central design objectives: avoiding new fixing-related interruptions to the waterproofing.

The wider roof performance still depends on the waterproofing, drainage and maintenance of the complete construction.

The significance of the system was that the guarding strategy did not require the project team to introduce the penetrations it was seeking to avoid.

Working above the waterproofing Select an image to enlarge

Roof surface visible between the frame members
Deck support and frame above the exposed roof surface
Perimeter posts and supporting frame before decking

Engineering the decking and guarding together

The completed terrace incorporated approximately 25 linear metres of Milano balustrade in a black finish.

A key aspect of the project was the relationship between the decking boards and the supporting frame.

The selected timber decking incorporated two anti-slip strips per board, formed using a resin-bound aggregate treatment.

The board characteristics and support arrangement had to be considered together.

Balconette undertook internal testing to investigate the behaviour of the decking under the relevant loading conditions.

The purpose was to understand how the boards deflected and how that behaviour affected the supporting frame configuration.

The results informed the design of the frame and its relationship with the decking.

This project-specific work was particularly important because the system needed to accommodate the variable roof levels while providing the required structural support.

Decking and guarding details Select an image to enlarge

Timber decking boards with two anti-slip strips
Detail of the black Milano balustrade

Designing around the building's setting

The Rights of Man occupies a prominent position within Lewes's historic townscape.

The project needed to introduce a contemporary external terrace without losing sight of the character of the surrounding buildings.

The castle forms part of the wider visual setting.

The Milano balustrade was selected for its appearance, providing a black metalwork finish to complement the refurbished terrace.

The contrast between the contemporary terrace components and the older building fabric became part of the architectural solution.

However, the aesthetic decisions were closely connected to technical considerations.

The balustrade needed to achieve the required geometry and loading performance, while the deck had to establish a consistent level above the irregular roof.

The project therefore required the visual design and structural arrangement to be developed together.

Installation in the centre of Lewes

Access was a significant practical constraint.

The narrow streets and tight approach routes around the pub restricted how materials could be delivered and handled.

The project team used a lorry-mounted crane to lift materials to terrace level.

This required coordination of deliveries, lifting arrangements and the available site access.

Once materials were positioned, Balconette's installation team completed the terrace works over 11 working days.

The relatively restricted working environment made preparation particularly important.

Components needed to arrive in the correct sequence, and the installation team had to work around the existing building geometry.

The adjustable frame arrangement helped accommodate the differing roof levels without requiring the finished deck to follow the uneven surfaces below.

The project demonstrates the importance of considering installation logistics alongside the structural design, particularly where a roof terrace is being refurbished in a constrained town-centre location.

Installation in progress Select an image to enlarge

Lorry-mounted crane at the Lewes site
Supporting frame with timber boards stacked ready for installation
Timber decking partly laid over the supporting frame

The completed terrace

The finished project provided approximately 83 m² of external terrace space, with a consistent walking level across the previously uneven roof areas.

The installation incorporated approximately 25 linear metres of black Milano balustrade and timber decking with integrated anti-slip strips.

The renewed roof waterproofing remained separate from the conventional penetrative balustrade fixing approach that the design team had sought to avoid.

The terrace was installed over 11 working days, following coordination between Balconette, the architects and the main contractor.

The result brought together three distinct requirements: a level usable terrace, a contemporary guarding arrangement and a non-penetrative solution above the renewed roof.

Views of the completed terrace Select an image to enlarge

Finished timber terrace overlooking the Lewes roofline
Finished timber terrace and black Milano balustrade from another angle

Why the project matters

The Rights of Man illustrates a common difficulty in roof terrace refurbishment.

The visible design objective may be relatively straightforward: replace an ageing terrace with a new deck and balustrade.

But the underlying construction can present a more complicated set of constraints.

Existing roof levels may differ. Waterproofing may have a history of failure. Structural support needs to be established. Access can restrict the installation method.

If the decking and guarding are designed independently, those interfaces may only become apparent once the work is under way.

At the Rights of Man, the project team considered the roof, supporting frame, decking and balustrade together.

That approach allowed the design to respond to the uneven roof geometry while avoiding new conventional guarding penetrations through the renewed waterproofing.

For architects and contractors working on existing buildings, the project demonstrates why the supporting construction deserves as much design attention as the finished terrace.

The critical question is not simply what the terrace will look like.

It is how the complete assembly will be supported, levelled, waterproofed and installed within the constraints of the existing building.

Project specification

Item Detail
Location Lewes, East Sussex
Building Rights of Man public house
Architect Mackellar Schwerdt Architects
Main contractor JH Payne Building Contractors
System BalcoDeck®
Balustrade Milano
Balustrade finish Black
Terrace area Approximately 83 m²
Balustrade length Approximately 25 linear metres
Decking Timber with two resin-bound aggregate anti-slip strips per board
Roof configuration Existing roof areas at differing levels
Design approach Adjustable supporting frame and non-penetrative guarding arrangement
Installation 11 working days
Completion Spring 2026